Investment case¶
An investment case compares each scenario with a baseline and reports whether the extra capital pays for itself: payback, net present value (NPV) and return on investment (ROI). It is computed from a scenario run, so set the scenarios up first (see Experiments).
Setting it up¶
The model's investment section:
| Field | Meaning |
|---|---|
baseline |
the scenario everything is compared with; empty means the model as saved |
horizon_years |
years the saving is counted over, default 5 |
discount_rate |
per year, default 0.08 |
operating_hours_per_year |
default 4000; the run is scaled to this many hours |
margin_per_part |
money earned per extra good part, default 0 (a pure cost case) |
throughput |
the KPI that counts good parts; empty means completed entities |
Mark each upfront investment with capex: true on its row of fixed_costs. A
capex cost still appears in Total Cost as before; the investment case alone treats
it as capital instead of operating cost. A fixed cost without it is scaled to a year
with the rest of the run's cost, so give it as the amount for the run window, not for a
year.
A scenario can change a fixed cost but cannot add one. Give the saved model the investment's row with amount 0, and let the scenario set the amount:
"fixed_costs": [{"name": "Robot cell", "category": "Capital", "amount": 0, "capex": true}],
"scenarios": [{"name": "Robot cell",
"overrides": [{"path": "fixed_costs.Robot cell.amount", "value": 85000}]}]
What is computed¶
For each scenario, with its own observed run window scaled to a year:
- Capex: the sum of its
capexfixed costs. - Operating cost per year: (
Total Costminus capex) scaled to a year. - Parts per year: the throughput scaled to a year.
Against the baseline:
- Extra capex: capex minus the baseline's.
- Saving per year: the baseline's operating cost minus the scenario's, plus
margin_per_parttimes the extra parts per year. - Payback years: extra capex divided by the yearly saving, not discounted. "never" when there is no saving; 0 when the scenario needs no extra capital.
- NPV: minus the extra capex, plus each year's saving discounted at
discount_rateover the horizon (a part year counts pro rata). - ROI %: (horizon times saving, minus extra capex) over extra capex.
Saving and NPV carry a 95 % confidence interval over the replications; scenarios share random numbers, so the interval is on the difference, replication by replication. One replication gives no interval.
Where to read it¶
naga invest MODEL, or the "Investment" sheet ofnaga scenarios --out file.xlsx.nagasim.investment.investment_case(result, layout)in a notebook.- The agent tool
investment_case.
The bundled model automation_cell is a worked example.
Not included¶
Tax, depreciation, financing, discounted payback and a sensitivity table. Run the study again with other inputs to see how the case moves.