Planning and scheduling

An order book (the bundled model order_due_dates) answers "what happens if this shop runs". A planner asks three narrower questions instead: what is the plan, is there a better one, and how risky is it. naga plan answers all three from one model.

What is the plan: deterministic mode

Set simulation.deterministic: true (or pass --deterministic/deterministic=True to the notebook API) and every random draw becomes its own mean instead of a sample: a distribution returns its closed-form mean, a DECIDE-by-chance branch splits by largest-remainder allocation instead of a coin flip, and replications are forced to 1. One run is then a single, reproducible timeline -- the plan -- rather than one sample among many.

This also turns on schedule_log: one row per resource hold (order, block, resource, start, end, setup share), drawn as a Gantt chart by resource or by order in the HTML report's Schedule section. outputs.schedule: true turns the same frame on in an ordinary stochastic run, if you want the timeline without going deterministic.

Deterministic mode is a mean-value model, not a fluid limit: because of queueing and branching, the mean of many random runs is not the same number as one run of the means. Use it to see the plan's shape, and plan risk to see how much a real shop would vary around it.

Handing the plan to an MES

plan_export(schedule_log, path) (Python) or naga plan model.json --export plan.csv (CLI) writes the schedule as a plain CSV or JSON by the path's extension -- Order, Operation, Resource, Planned Start, Planned End, plus dated columns when the model has a calendar (Dates and calendars). This is a one-way hand-off: nothing is read back from an MES here.

How risky is it: plan risk

planning.plan_risk(layout, replications) runs the SAME layout twice over: once deterministically for the plan, then N times with the model's own randomness and queue discipline left alone. The result, one row per order:

Column Meaning
Planned End the deterministic plan's own completion time
P(On Time) share of replications where the order finished by its due date (an order that never finished counts as late)
Mean Lateness / P90 Lateness signed lateness (end - due) across the replications that finished
Mean End mean completion time across the replications that finished

naga plan model.json --risk 200 prints this table.

Is there a better one: the CP-SAT proposer

cpsat.propose(layout, objective="makespan"|"weighted_tardiness") reads the order book as a job shop -- each order's routing sequence (as in the bundled model job_shop_routed) is a machine routing, its processing time the deterministic mean of the station's PROCESS -- and solves it with OR-Tools CP-SAT. It needs the optional ortools package (the plan extra: pip install "nagasim[plan]"); without it, --propose prints a clear message and exits with status 2.

The result is an ordinary scenario: every order gains a plan (its planned start per station) and, where the plan starts it later, a later release; every resource the plan uses gets the new Plan queue discipline, which dispatches each station in the planned order. The proposal is not applied automatically -- run it through plan_risk or the deterministic plan again to see what it does, exactly as you would any other scenario.

Not every routing survives the trip through the solver. Refused features (ROUTE by expression, BATCH/SEPARATE, conveyors, worker/vehicle fleets, capacity schedules and failures, setups outside a single-unit resource) are listed on the result and left out of the CP-SAT model, but the simulation still executes them exactly as written -- the solver proposes, the model still decides what actually happens.

The plan CLI

naga plan order_due_dates
naga plan order_due_dates --risk 20 --export plan.csv --report plan.html

The other options are --orders orders.csv, --propose makespan|weighted_tardiness, --time-limit S and --workers W.

--orders replaces the model's order book from a CSV. With no other flag it just prints the as-is schedule; add --propose to solve first (the proposed layout, not the as-is one, is what --risk/--export/--report then use), --risk N to score it, --export to write it, and --report for an HTML page with the Gantt and the risk table together. See the command line reference for every flag's default.